PEPE POPPERS DBO BED BED BED BAD BED IAB OEE PEE PEPER ASBE SLOs 1975 CASSIAR, BC. oy 4 VOLUME 18 oy MELT ES’ SEY ee Ae GASSIAR’S, TRAMLINE THE NEW $5,000,000.00 TRAMLINE DELIVERED ITS FIRST TON OF ORE TO THE MILL AUGUST 19TH, 1975, THE LONG AWAITED DAY HAS ARRIVED AND AFTER TWO YEARS OF PLANNING AND CONSTRUCTION THE ORE WILL BE DELIVERED TO THE MILL FROM NOW ON BY THE NEW LINE. THIS WILL ELIMINATE THE ORE TRUCKS HAULING FROM THE MINE AS THEY HAVE BEEN DOING FOR THE PAST FIVE YEARS AND ALSO ELIMINATE THE OLD TRAMLINE THAT HAS BECOME OBSOLETE ‘AND FAR UNDER CAPACITY, THERE MAY BE A FEW MINOR ADJUST- MENTS TO MAKE BEFORE ALL THE KINKS ARE ELIMINATED BUT EVERYONE HAS HIGH HOPES FOR ITS CAPABILITIES, THE ORE WILL STILL BE CRUSHED AT THE MINE SITE BEFORE IT IS LOADED INTO THE NEW CARS WHICH HOLD 1 3/4 TONS EACH AND TRAVEL AT 7 MILES PER HOUR WITH A CAPACITY OF 300 TONS PER HOUR, THE OLD ROCK REJECT AT THE MINE WILL BE FLIMINATED AND ALL OF THE ORE WILL BE DELIVERED TO THE MILL WHERE IT WILL GO THROUGH 2 HAZAG CRUSHERS BEFORE wii TO DRYERS AND THE DRY STORAGE BUILDING, WITH 300 TONS PER HOUR, THE MILL WILL BE ABLE TO OPERATE AT FULL CAPACITY AND BY ELIMINATING THe OLD ROCK REJECT THE MILL WILL BE ABLE TO RECOVER THAT EXTRA 1% OR BETTER OF FIBRE THAT HAS BEEN LOST OVER THE PAST FEW YEARS, PROGRESS IS ALWAYS GOOD AND ELIMINATING WASTE IS PART OF PRODUCTION. oil agg ON THE COMPLETION OF A BIG JOB,