Applying “steelcrete”’ as part of the ground support at McDame. McDame Project D evelopment of the McDame project commenced in 1988, heralding the end of the open pit era at Cassiar and initiating the transition to underground mining. Mining Plan At present, underground development is scheduled to be finished in March, 1990, well ahead of the completion date originally projected of October, 1990. The mine is expected to achieve its full production rate of 5,500 tonnes per day by the end of that year, making it one of the largest underground mining operations in British Columbia. In order to achieve that high daily rate, a block caving mining method will be used. Key management personnel, experienced in using this low-cost technique for mining asbestos have recently joined the McDame team, and their expertise will greatly facilitate our move from open pit to underground mining operations. An adit into the side of McDame Mountain will provide access to the ore body and a ramp will lead down to the various mining levels. Ore from the drawpoints will be dumped into an ore pass and then conveyed out of the mine. The existing tramline will be shortened, once the open pit mining is complete, to deliver the McDame ore to the mill. Progress Made in 1988 Surface development for the project started in the second quarter, while the contract for the underground work was being awarded. Underground work was initiated in early July. This consisted of slashing 1,295 metres of the main access drift, driving 225 metres of conveyor decline and completing a 48 metre ventilation adit. In total, $8.6 million was spent on the project in 1988. Development Costs Since many of the existing plant facilities and services for the open pit operation will be used by the McDame project, the capital costs for its development are significantly lower than they would be for a totally new operation of similar scale. At present, the total cost of bringing the new mine into full production is estimated to be $48.1 million, including $7.8 million for secondary development during the preproduction period but excluding the originally planned secondary concentrator. Mine access development is higher than originally estimated, because more ground support is projected to be installed in the main access drifts and conveyor decline. Mining during the gradual production build-up in 1990 will yield 467,000 tonnes of ore, with a fibre value of $17 million. Although original plans called for a secondary concentrator to be added to the present milling facilities, modifications which have improved the rejection rate of the primary concentrator make this unnecessary to meet forecasted production. A $25 million development loan from the B.C. Government, repayable from 50 percent of the cash flow generated from the asbestos assets, covers part of the capital cost of the project. Bank financing will provide another $9.6 million. The remainder will come from cash flow internally generated by Cassiar open pit operations. Reserves The production layout provides for mining 16 million tonnes of ore, with a mill yield of 5.6 percent fibre. These reserves will provide mill feed for a period of 10 years. Diamond drilling will be undertaken this spring to define additional reserves that were indicated in a southerly extension by drilling carried out in 1984.