“THE CASSIAR STORY” Mining Gillyeard J. Leathley, General Mine Superintendent, Cassiar Asbestos Corporation Limited, Cassiar, B.C. Abstract The Cassiar Asbestos mine is situated on McDame Mountain in northern B.C. at a mean elevation of 6000 ft (1830 m), some 6 miles (9.6 km) from the townsite/mill complex. Asbestos ore production averages 1,200,000 tons at 9% R.M.G. (Recoverable Mine Grade) and waste produc- tion is 6,000,000 cu. yd annually. Waste is loaded by P&H 1900 AL 11-cu.-yd shovels and transported by 75-ton and 85-ton end-dump trucks to the waste dumps. The ore is loaded by a 992 Caterpillar 10-cu-yd front-end loader into 50-ton and 75-ton trucks, which trans- port it to the crushing plant located at the mine. The ore is transported by a 15,370-ft (4685-m) tramline to the mill complex. Introduction THE CASSIAR OPEN-PIT MINE is situated at a mean elevation of 6000 ft (1830 m) on McDame Mountain, 6 road miles (9.6 km) from the main mill/ plant complex. The access road rises some 2350 ft (716 m) from the plantsite to the mine by means of a series of tight switchbacks. Constant grading is required with a Caterpillar 16G grader to ensure that drainage ditches are kept clear to deal with a heavy spring snow melt and an annual summer rainfall of 12 in. (300 mm). During winter, the grader is equip- ped with a front snow blade, as well as a rear-mounted hydraulically operated snow wing, and the use of tire Gillyeard J. Leathley was born and educated in Scotland. He graduated from Glasgow’s Royal College of Sci- ence and Technology, with a Higher National Certificate in mining and mine surveying. He joined the Na- tional Coal Board (Scotland) in 1952 and worked as a mine surveyor and work study engineer in underground — coal mines. In 1962, he joined Anglo * American Corporation, Zambia, as a learner mine official and was later assistant manager, Open Pit Division of AMCO, respon- sible for open-pit coal and copper mines. Returning to Scotland in 1967, he joined a rock excavation company in the United Kingdom and served as a director of the company until 1971. At that time, he became mine tech- nical superintendent of Guyana Bauxite in South Amer- ica, progressing to general mine superintendent in 1972. In this position, he was responsible for the operation of six nationally owned bauxite mines producing 5,000,000 tons of bauxite annually, with the removal of 30,000,000 cu. yds of overburden. Experience in the operation of bueketwheel excavators, walking draglines and rail min- ing was gained at this time. In 1975, Mr. Leathley joined Cassiar Asbestos Corpora- tion Limited as chief engineer. He is now general mine superintendent responsible for the complete operation of the engineering and mines departments. He is a member of the CIM. Keywords: Cassiar mine, Asbestos, Open-pit mining, Drilling, Blasting, Lauding, Haulage, Mining methods, Dewatering, Crushing. chains is standard to deal with 13 ft (400 em) of snowfall annually (Fig. 1). Personnel are transported to the mine by a 45-seater manhaul bus, supplemented by 4x4 pickups equipped with 14-seat passenger carry cabs. The pickups allow operators to change over at the equipment location, reducing equipment downtime. The 1977 production was 1,321,065 tons of ore and 6,874,201 cu. yds of waste rock, which meant a strip- ping ratio of 1 ton of ore to 5.20 cu. yds of waste. The five-year mining plan, which is updated and revised as sales commitments and mining conditions dictate, envisages approximately the same magnitude of ore for the next 14 years, with waste production conti- nuing at 6,000,000 cu. yds until Phase 9 waste is excavated by the end of 1985. An increase in waste-rock production, dictated by the introduction of additional milling facilities re- quiring an increase in asbestos ore, as well as an in- creasing stripping ratio, led to the introduction of a 1900 AL P&H 11-cu.-yd shovel in October, 1974. An additional 1900 AL P&H 11-cu.-yd shovel was intro- duced in October, 1975. This necessitated pit electri- fication, which was completed in October, 1974, and the introduction of a fleet of 85-ton Euclid trucks. The following figures give some indication of the progress of the mine since production commenced in 1954: Waste Cubic Ore Tons Yards TOSS OGOE An ee deerme tans 2,266,761 2,977,458 SG 0/3197 ON nares seers ce 7,907,277 17,217,172 RVR eeuissiacwone coschorte 5,376,551 13,786,669 1975 — December 1977.............. 2,244,616 13,600,575 TOIAISIREMOVED Reepetecrsecta te tepre 17,795,205 47,581,874 REMAINING TO END OF PLANNED PT (Leos. Sbeknbodesascean anon 16,277,000 48,042,000 The phase mining plan dictates meticulous planning of ore and waste scheduling to ensure a continuous supply of ore to the mill, especially during the inter- phase period. Phase mining configurations are shown in the paper dealing with the planning operation. The assistant mine superintendent and the general foreman - mine, work very closely with the planning and geology departments to ensure that long-range plans and monthiy schedules are adhered to. It is the responsibility of this group to ensure that adequate ore supplies are available to blend low- and high-grade areas or supply ore from a high-grade, long-fibre area if a spinning-grade fibre run is required in the mill. A planning meeting to relay this information to the mine shift foreman is held every two weeks to allow discussion and examination of the developed plans. Mill requirements regarding the type and/or blending of ore required are marked daily on a location plan in the mine shift foreman’s office at the mine. If the mine foreman must deviate from this plan, he is re- quired to inform the mill shift foreman immediately to allow the mill to relocate the ore in the dry rock storage to a more suitable area. No designated ore can be discarded unless agreed to by the geology de- partment. A monthly reconciliation of ore predicted by the geologist, and typed by him from production drilling and actual ore mined, is carried out to ensure that a minimum amount of ore is discarded. Unfor- = BES