Cassiar Asbestos Corporation Limited Report of the General Manager Mr. F. M. Connell, President, Cassiar Asbestos Corporation Limited, Suite 1001, 85 Richmond Street West, Toronto 1, Ontario. Dear Sir: I submit herewith my report on operations during the fiscal year ended September 30, 1956. Mine During the fiscal year, 356,334 tons of ore were delivered to the millsite and 406,118 tons of waste rock were removed from the hanging wall of the orebody. Due to favourable weather conditions, waste removal commenced on April 11, 1956 and the first ore of the season was delivered on May 1, 1956. Mining continued until October 28, 1956, and 342,903 tons of ore were delivered and 411,020 tons of waste were removed, or an average of 1,715 tons of ore and 2,055 tons of waste per day during the period April 11 to October 28. The tramline was put into Operation on June 1, 1956 and handled 50% of the total tonnage. Some alterations are required in the loading arrangements to permit use of its full capacity of 100 tons per hour during the cold periods in the early spring and late fall. Detailed studies of mining methods have resulted in a long-range programme of development for the mine, which will be carried out over a number of years. Because of the topography in the vicinity of the orebody, waste rock from the hanging wall must be removed well in advance of the ore mining operation. In order that there be no interruption to future operations, this work was started during the current year. The total expenditure amounted to $390,255. Pace NINE