slumping and cracking of the dumps dictate the need for good maintenance practices. Haul lengths vary depending on location, with averages of 2500 ft (762 m) one way, uphill hauls comprising about 50% of the production time. Tire wear is a major concern during spring and summer, as the combination of water and extremely sharp-edged rock fragments cause serious tire damage unless the roads are well graded and drainage ditches installed. A revised tire maintenance program begun one year ago with the assistance of a major tire supply company is already paying dividends. It is proposed to extend this tire maintenance program whereby a contract will be entered into with a tire company and tires will be supplied on a unit-cost-per-hour basis. Chains are used on graders and some support ve- hicles, such as the mobile lubrication truck which serv- ices the equipment in the field. Major repairs to trucks are carried out in the mine garage, located in the pit. The facility consists of five truck bays, a welding bay and a steam bay. Ore Mining Mining of ore is carried out 260 days per year, three shifts per day, with two days of scheduled mainte- nance each week on the crushing plant and tramline. The daily production rate is 5000 tons, with an aver- age recoverable mine grade (R.M.G.) of 9%. Drilling of the ore and serpentine host rock is per- formed with a diesel-powered Robbins R108, mounted on an International TD25 tractor, utilizing a 9-in.-dia- meter hole and capable of drilling 60 ft (18.2 m) if required. Prior to drilling, the area is levelled and prepared for the surveyors to mark out the required drill pattern. Patterns vary from 22 ft (6.7 m) by 22 ft in the summer to 18 ft (5.5 m) by 18 ft in the winter months on a 30-ft. (9.1-m) deep bench. The top 3 to 4 feet of the ore bench are saturated with water during the summer, therefore, once freezing conditions pre- vail, this portion freezes and is very difficult to frag- ment during blasting. On occasion, holes 8 ft (2.4 m) deep are drilled between each row of production blast holes, charged with 25 lb of explosives and blasted with the main blast to try to alleviate the problem of large blocks of ore being produced after blasting. This blocky ore is extremely difficult to fragment in the jaw crusher. To help reduce orebody saturation caused by water, ditches and culverts are installed in the sum- mer to control and direct water to the dewatering sump. FIGURE 6 — Double-side shovel loading after a typical blast. The ore mining sequence is dictated by the sales commitments, and a three-month mining plan is drawn up each month and revised as required. Blending of ore in the pit is practised under the supervision of the mine geologist, with all information required being recorded in the mine foreman’s office. Contamination of ore by foreign objects cannot be tolerated and great care is taken to ensure cleanliness, both on the ore bench and during the ore crushing cycle. No subgrade drilling is practised, as the ore is relatively easy to blast at a normal charging ratio of 0.4 lb per ton. Whenever possible, ANFO is used, with excellent results. Drill holes are not normally pumped in the asbestos ore, as no polyethylene liners can be used. A special explosive, “Cilgel”, has a package covering that conflagrates during the blast. All blast initiations are carried out using a capped fuse attached to primacord in preference to electric blasting, thus preventing ore contamination by lead wires. After the blast, the bench is levelled to ensure that during winter any heavy snowfall can be cleaned off the ore prior to sending it to the crushing plant. Fragmentation of the asbestos ore is controlled to ensure maximum rejection at the mill concentrator, thus ensuring that no un- necessary rock is dried or milled. A 30% rock rejec- tion is the scheduled target at the concentrator. Loading of the ore is carried out with a Caterpillar 992 front-end loader, equipped with a 10-cu.-yd bucket and beadless tires (linked tracks similar to tractor pads), which have proved effective in reducing tire spin, thus reducing rubber contamination in the ore. Whenever possible, serpentine waste rock is made available to enable the loader to load ore and waste. As the loader is radio equipped, the crusher operator can direct the ore trucks to waste and inform the loader operator when the next requires ore. The ore haulage fleet consists of five 50-ton Wabco trucks, equipped with VTA 1710 12V 635-hp Cummins engines and Allison 6061 transmissions. Normally, two trucks are running during the ore cycle. If waste is available close by, an additional truck is added to the fleet. Truck counts are taken of the ore hauled to the crusher; a survey check is made and the ore is weighed at the mill. This has established that the 50-ton Wabco trucks average 44 tons per load. Haul roads are kept at an 8-10% gradient whenever possible. Salt and sand are used during winter months and crushed gravel is spread on the main footwall haul road to ensure good drainage. Dewatering Pumping is required to ensure that the ore is kept as dry as possible (so that less fuel will be required for ore-drying) and to ensure good access to the ore during the spring melting and the summer rain periods. Snow is normally cleaned from the catchments and the pit area in April to minimize the inflow of water from the snow melt. A truck equipped with a 4000-gallon tank is used to haul water out of the pit until such time as the electric submersible pumps and the 8-in.-diameter pipeline can be installed (in May) without freezing problems. A 2250B Flygt pump, rated at 700 gallons per minute, with a combined static and friction head of 215 ft (65.5 m), is installed in the sump at the pit bottom (5570-ft elevation on Phase 7). The pump is installed on a base made from 6-in. ‘Tl beams to ensure that the suction inlet is clear of the sump bottom, as the long asbestos fibre tends to block — 28 —